The pipelines have been replaced; preparations are ongoing to restart the power plant

On Saturday, the welding of the second new segment of the pipeline in the so-called valve room in the containment was completed. The quality of the welds was confirmed by non-destructive methods. With this, the replacement of pipelines was completed and preparations for restarting the power plant began.

According to the outage plan, 121 fuel elements are being transferred from the Spent Fuel Pool back into the reactor vessel. Once this transfer is complete, the heating of the systems will follow; their operation will be verified with an extensive surveillance testing program. We plan to synchronize the generator with the power grid in mid-November.

News

Root Cause Analysis of the Leak in the Safety Injection System Pipeline Completed

More
Obvestilo

Merry Christmas! May the year 2025 be successful and full of the right energy!

More
News

In half a century after the laying of the foundation stone, more than 220 billion kilowatt hours of electrical energy

More